Construction Change Orders: Why They Happen, What They Cost, How to Cap Them

A change order is a signed agreement between owner and contractor that changes the contract after it is signed: it adds, removes or alters work, and adjusts the price, the schedule or both. Every renovation has some. What separates a controlled project from a painful one is how many there are, what causes them, and whether each one is priced and approved before the work happens.

Key takeaway. A change order formally changes scope, price and time after the contract is signed. Its cost is the direct cost of the work plus the contractor's agreed markup plus any extra time on site, and it rises the later the change is made. On clinic renovations most change orders come from five predictable sources, and most of them can be reduced before construction starts.

What Is a Change Order?

A construction change order is the paperwork that keeps the contract true to the job. When the owner wants something different, when the site turns out to be different from what the drawings assumed, or when an authority asks for something nobody planned for, the contract no longer describes the work being done. The change order fixes that, in writing, with both signatures.

A complete change order says:

A change order is not a failure. It is the mechanism that lets a contract adapt to a real building without anyone arguing about it later.

Change Orders vs. Change Directives

Most commercial work in Canada is contracted on the Canadian Construction Documents Committee's CCDC 2 stipulated price contract or a form based on it. Its Part 6 (Changes in the Work) gives the owner two ways to change the work, explained clearly in this summary of CCDC 2's General Condition 6:

The change directive exists so a disagreement about money does not stop a job. It is also more expensive to administer, because every hour and invoice has to be tracked. Use it when you must, not by default. If your contract is not a CCDC form, read its changes clause before construction starts — it governs everything in this article.

How a Change Is Priced

A contractor pricing a change builds it up from the same components as the original bid:

Credits work in reverse, but rarely at full value. Material already ordered, fabricated or delivered cannot always be returned, and the contractor's overhead does not shrink because one item came out. Expect a deleted item to credit less than it would have cost to add.

Our article on how contractors price a commercial project explains how the original bid is built, which is the baseline every change is priced against.

What a Change Costs Beyond the Price

The number on the change order is rarely the whole cost. A change also costs:

This is why timing matters more than almost anything else. The same change made on paper during design, made after tender, and made after the work is built can cost very different amounts.

The 5 Most Common Causes of Change Orders on Clinic Jobs

  1. Concealed conditions. What is behind the walls, under the floor and above the ceiling of an existing space: undersized drain lines, abandoned services, structural surprises, and hazardous materials such as asbestos. In an older building, a hazardous materials survey before renovation moves the biggest of these from a mid-job change to a known line in the bid.
  2. Equipment changes after rough-in. Dental chairs, imaging units, sterilisers and compressors each come with vendor requirements for power, water, drainage, venting and blocking. Change the model after the rough-in is set and the rough-in changes too.
  3. Owner design changes during construction. Moving a wall, adding an operatory, changing a finish once the space can be walked. Some are worth it; all are cheaper on paper.
  4. Uncoordinated drawings. Architectural, mechanical and electrical drawings that each work alone but collide in the ceiling. A clinic's ventilation, plumbing and medical gas or vacuum lines make this more likely than in an office fit-out.
  5. Authority and landlord requirements. Building inspector comments, health authority conditions, fire department requirements and landlord base-building rules that surface after pricing.

The dental office renovation checklist sets out the order of decisions that heads off most of these on a dental project.

A Sample Change-Order Log

A change-order log is a single running list of every proposed and approved change. It is the document that lets an owner see the true contract value at any point. The entries below are illustrative only — they show the format, not a real project — and price columns are deliberately left as the basis of pricing rather than figures.

CO #Date raisedDescriptionCausePricing basisTime impactStatus
001Week 2Replace corroded cast-iron drain found under slab at operatory 3Concealed conditionPlumbing subtrade quote + agreed markupClaimed — on critical pathApproved, signed
002Week 3Revise chair rough-in for owner's new chair modelEquipment changePlumbing and electrical quotes + markupNone claimedPriced, awaiting owner
003Week 4Delete feature wall tile in reception, substitute paintOwner design changeCredit: material not yet ordered, less restockingNoneApproved, signed
004Week 5Add fire damper at relocated duct penetration per inspectorAuthority requirementChange directive — cost + allowanceTo be assessedProceeding under directive
005Week 6Reroute sprinkler branch clashing with new bulkheadUncoordinated drawingsSprinkler subtrade quote + markupNone claimedUnder review

Keep the log in a shared file, update it weekly, and add three totals at the bottom: approved changes, pending changes, and remaining contingency.

How to Cap Change Orders

You cannot eliminate change orders on a renovation. You can keep them small, priced and predictable.

Conclusion

A change order is how a construction contract keeps up with a real building. The cost of each one is direct cost plus agreed markup plus time, and that cost rises the later the decision is made. On clinic renovations, concealed conditions, equipment changes, design changes, uncoordinated drawings and authority requirements cause most of them, and each can be reduced before construction starts. Agree the pricing rules in the contract, keep a weekly log, and approve nothing verbally. If you are planning a renovation and want the change-order rules agreed before the first wall comes down, our commercial renovation page covers how we run this work.

Frequently asked questions

What is a change order in construction?

A change order is a written agreement, signed by the owner and the contractor, that changes the contract after it has been signed — adding, removing or altering work and adjusting the contract price, the schedule or both. Under the standard Canadian stipulated price contract, CCDC 2, a change order records a change both parties have agreed; a change directive is used when the work has to proceed before the price or time is agreed.

How much does a change order cost?

There is no fixed figure. A change is priced as the direct cost of the labour, material and subtrade work involved, plus the contractor's agreed markup for overhead and profit, plus any extra time on site the change causes. Under CCDC 2, a change directive is valued on actual cost plus an allowance for overhead and profit. The cheapest change is one decided before the work it affects is built.

What causes the most change orders on a clinic renovation?

Five causes account for most of them: concealed conditions found behind walls and ceilings, equipment specifications that change after rough-in, owner-requested design changes during construction, drawings where the mechanical, electrical and architectural layers were never coordinated, and comments from the building inspector, health authority or landlord that require work nobody priced.

Can a contractor do extra work without a signed change order?

They should not, and a well-written contract says so. Extra work done on a verbal instruction is the most common source of end-of-job disputes, because the owner remembers a small favour and the contractor remembers a priced extra. Require a written change order, or a written change directive where the work cannot wait, before any change proceeds.

How do you limit change orders on a renovation?

Finish the design before tender, investigate concealed conditions before pricing, lock equipment selections before rough-in, agree the markup rate and pricing method in the contract, carry an owner-held contingency, and name one person on the owner's side who can approve changes. None of these eliminate changes; together they keep them small and predictable.

The service this article is about

Renovations planned around how the space needs to function before demolition, trades, and finishes begin.

Commercial Renovation →