Leases & Planning6 min read
How to Open a Dental Office in BC
Opening a dental office in BC is a site decision, a lease and a municipal building permit. The BC College of Oral Health Professionals registers the dentist. The city permits the building. This guide is the order we use for clinics in the Lower Mainland. It uses only the cost band and the timeline ranges already published on this site.
Key takeaway. Choose a shell that can take dental plumbing before you sign. Fix every chair position before rough-in. Plan on 6–12 weeks of design, 6–16 weeks of permits and about 10–16 weeks of construction after the permit. The published dental band is $300–$450 per square foot across the Lower Mainland.
Site selection
Patients have to reach the suite. The base building has to accept extra plumbing. Rent is the third question.
Three shells show up again and again. A strata unit under apartments shares the elevator, the loading dock and a noise bylaw. A street plaza usually has easier hours and a thinner electrical service. A purpose-built medical building is the easier shell only when the last tenant was clinical. A former office in that building still needs vacuum, compressed air and a drain at every chair. Do not treat a corridor riser as a dental line until someone has traced it.
The shell is different in each city we have written up.
Vancouver dental clinic construction covers street-front space and podium suites. The city uses the Vancouver Building By-law.
Burnaby dental clinic construction follows Metrotown, Brentwood and Lougheed. Most new suites sit under occupied apartments.
Richmond dental clinic construction splits No. 3 Road medical floors from older Steveston units. Commercial files go through MyPermit. An incomplete package is not accepted.
Coquitlam dental clinic construction puts Town Centre and Burquitlam podiums next to older units in Austin Heights and Maillardville.
North Vancouver dental clinic construction splits the City on Lonsdale and Marine Drive from the District in Edgemont and Lynn Valley.
Read the page for the city named on the lease. The differences are permit facts.
The lease
The owner has to allow the work. Get that permission in the lease before you sign. An allowance is money toward the fit-out. It is not a construction quote. Ask what stays when you leave. Partitions, ceilings and plumbing rough-in usually stay with the suite. Chairs and sterilizers that the practice owns usually leave with you.
Strata hours should be known before the signature. So should any opening in a common slab. Both are expensive to discover after the lease is signed.
Use the clinic lease checklist on the suite you are about to sign. The construction meaning of the work you will pay for is on the leasehold improvements page. Tax treatment of that spending is a different article.
Permits and municipal approvals
The building permit is issued by the municipality. The college does not issue it.
Vancouver reviews this work under the Vancouver Building By-law. It does not use the BC Building Code. The city also runs an office Tenant Improvement Program. That programme does not cover a dental fit-out. A dental suite uses the standard building-permit route. The wider sequence is in medical clinic construction permits in BC.
Other cities publish their own forks. In Burnaby a plan checker chooses the fast track or a full review. Fraser Health approval removes the fast track for the personal-service uses the city lists. Those published examples are salons, esthetics and skin care. In Richmond the drawing set has to be complete before MyPermit will take it. In Coquitlam the file does not start without the owner's permission. A clinic that adds significant plumbing sits outside Coquitlam's fast track for retail and regular offices. In the District of North Vancouver most tenant improvements need an architect under the Architects Act.
Design and operatory layout
Count the chairs you expect when the practice is full. Draw sterilization as a one-way dirty-to-clean route before millwork is ordered. Keep the public queue off the clinical path.
The drawing set should be prepared with CSA Z8000 expectations in mind. The building department should not be the first reader of the clinical layout.
One contract can hold the design and the construction. That model is the dental clinic design-build page. Room sizes and the four zones of a layout are in the dental office design layout guide. This page does not repeat those dimensions.
X-ray shielding drawn before walls close
Shielding is part of the wall. It is drawn before the walls close. The imaging equipment and the room layout set the assembly. Adding shielding after the drywall is up means opening that wall.
Put the imaging rooms on the permit set. A note that defers shielding until after the walls close is how that room gets rebuilt. The same drawing package should already show the sterilization route and the chair services. One set is easier to review than three that disagree.
Plumbing, compressed air and vacuum
Each chair needs three services in the floor or the slab. Vacuum. Compressed air. A dedicated drain.
Those lines are rough-in. They are not a finish you can slide over on opening week. Chair positions are locked before the concrete or the floor is closed. Moving one later means cutting that floor.
Size the compressor and the vacuum pump for the final chair count. A trunk line sized for opening day will not carry chairs you add later. New trunk lines are a second project. Tell the mechanical designer the mature count before the first sketch.
Timeline
Treat these as general Lower Mainland ranges. A single suite can sit outside them.
Design is often 6–12 weeks. Permits are often 6–16 weeks. Construction for a typical clinic is about 10–16 weeks after permits are in hand.
Chairs and imaging equipment often carry 12–20 week lead times. Order them when the drawings are settled. Waiting for the permit is how a finished suite sits empty.
A five-operatory clinic on this site was completed in 90 days when the equipment and the permits were already coordinated. That result is a delivered case. It is not the range to write into a lease.
The phase table is the dental clinic build timeline.
Budget
Dental clinic construction is published at $300–$450 per square foot. The band is for the Lower Mainland. It is not a Vancouver figure. It is not a Burnaby figure. Operatory count, suction runs and imaging shielding move a job inside the band.
Equipment the practice owns is outside that band. Chairs and sterilizers are a separate budget. Ask for the fit-out and the equipment on separate lines of the cost breakdown.
The longer article is dental clinic construction cost in BC. The service page that carries the same band is dental clinic construction.
Who registers the dentist
The BC College of Oral Health Professionals registers the dentist. The municipality issues the building permit. We do not describe a college review of the building plans. That review is not part of the permit path we file.
A college registration does not let a crew start work. A building permit does not register the practice. Keep the two files separate from the first meeting. The dentist's regulator and the city's building department do not substitute for each other.
Conclusion
Bring the address, the stage of the lease and the chair count at full capacity. We will tell you what has to be decided before construction starts.
The contract that holds design and construction together is dental clinic design-build. The scope and the published band are on dental clinic construction. You can also book a consultation.
Frequently asked questions
How long does it take to open a dental office in the Lower Mainland?
Design is often 6–12 weeks. Permits are often 6–16 weeks. Construction for a typical clinic is about 10–16 weeks after the permit. These are general Lower Mainland ranges. A five-operatory clinic on this site was finished in 90 days only because the equipment and the permits were already coordinated.
What does dental clinic construction cost per square foot?
The published Lower Mainland band is $300–$450 per square foot. It is not a price for one city. Operatory count and the base building move a project inside the band.
Does Vancouver's Tenant Improvement Program cover a dental office?
No. It is an office programme. A dental fit-out uses the standard building permit under the Vancouver Building By-law.
Who permits the building, and who registers the dentist?
The municipality issues the building permit. The BC College of Oral Health Professionals registers the dentist. The college does not issue the building permit.
When do chair positions have to be fixed?
Before rough-in. Each chair needs vacuum, compressed air and a dedicated drain. The compressor and the vacuum pump should be sized for the final chair count rather than the opening-day count.
The service this article is about
Dental clinic builds coordinated around operatories, sterilization, plumbing, electrical, cabinetry, and patient flow.
Dental Clinic Construction →Opening or moving a clinic? See healthcare clinic construction and our clinic launch incentives.
Related reading
Planning a build like this?
Before you commit to a space, drawings, a budget, or a construction timeline, book a consultation and we will tell you what has to be planned before construction starts.