
West Cordova residential build
West Cordova, Vancouver, BC
- Specialty
- Luxury residential
- City permit authority
- City of Vancouver — Development and Building Services Centre
Services
Healthcare
Healthcare ConstructionDental Clinic ConstructionDental Office RenovationMedical Clinic ConstructionPharmacy ConstructionPhysiotherapy Clinic ConstructionChiropractic Clinic ConstructionOptometry Clinic ConstructionVeterinary Clinic ConstructionClinic Renovation ContractorDental clinic design-buildMedical clinic interior designDental millwork and cabinetryDental equipment and plumbingX-ray room shieldingOperatory plumbing and vacuumDental clinic permits in BCBuying or starting a practiceDental office floor plansClinic Launch IncentivesCommercial
Commercial ConstructionCommercial RenovationOffice Renovation ContractorTenant Improvement Contractor
New Westminster Construction
A custom home is a finish schedule with a house attached to it. We plan that before the site gets busy. Drawings, permits and trades are sequenced by one team out of White Rock.
Experience
Jas Oberoi has run Oberizon from its White Rock office since 2021. Work near New Westminster runs through the same four stages.

We walk the space and price the risk before you commit to anything.
Drawings and permits go in while equipment and long-lead items are ordered.
One site lead holds the trades and calls you with progress every week.
Inspections cleared and the deficiency list closed before you take the keys.
The work

West Cordova, Vancouver, BC
Reviews
Very impressed with Oberizon Construction and the way they handled our dental clinic build. The team managed everything from planning to execution, and the final result was exactly what we envisioned.
We hired Oberizon to build out our dental clinic and they did an amazing job. The place looks so clean and modern, exactly the look we were going for.
Working with Oberizon on our dental clinic was a great experience from start to finish. Jas Oberoi and his team were professional, responsive, and genuinely invested in getting the details right.
Local planning
Oberizon works across the Lower Mainland, including New Westminster's historic and high-density commercial areas. Every project is planned around site access, inspection windows and how the finished space has to run.
New Westminster work is shaped by older building conditions, healthcare tenancy. We use that to set scope and sequence before demolition starts.
2026 range
$300–$400 per sq ft
turnkey — typically $1.4M–$1.8M for a 4,500 sq ft space
What that covers
What decides this build
The finish schedule is the critical path. Stone, millwork and specialty glazing are ordered against framing dates, because a six-week lead time discovered late is a six-week delay.
Long-lead items are ordered against the framing schedule rather than at finishing stage, and the site is protected to a standard that assumes the finishes are already installed. Most damage on a high-finish build happens after the expensive material arrives.
We walk the space and price the risk before you commit to luxury residential construction. Permits and services are the two that bite.
Stone, custom millwork and specialty glazing are ordered against framing dates rather than at finishing stage.
Protection is installed to a standard that assumes the finishes are already in. Most damage happens after delivery.
Where to go next
Questions
Yes. We run luxury residential construction across the Lower Mainland from our White Rock head office, and that includes New Westminster's historic and high-density commercial areas. Tell us the address and we will walk the space before you commit to anything.
New Westminster issues its own building permit, reviewed against the BC Building Code and the city's zoning bylaw, and the route differs from neighbouring municipalities. We confirm the current requirements with the city at the start of every job rather than working from the last one.
$300–$400 per sq ft turnkey — typically $1.4M–$1.8M for a 4,500 sq ft space. Base-building condition and finish level move that number most. The full 2026 breakdown is in the cost guide at /cost.
Most conversations start around Uptown, Downtown, and Sapperton. We travel further when the scope justifies it.
The address, your lease stage and a target opening date. Drawings and a budget range help. The more we know early, the tighter the feasibility comes back.
The finish schedule, not the framing. Stone, custom millwork and specialty glazing carry the longest lead times, so they are ordered against framing dates rather than at finishing stage.
Before the expensive material arrives, and to a standard that assumes it is already installed. Most damage on a high-finish build happens after delivery, not during construction.
Yes. A review finds the permit and service risks before you sign a lease or a design. That is the cheapest point to find them — a change after drawings are sealed costs weeks, not hours.
Before you commit to a space, drawings, a budget, or a construction timeline, book a consultation and we will tell you what has to be planned before construction starts.